Contracted Via: Bond Brothers
Started: August 2018.
Completed: March 2021 (Numerous phases)
Scope:
- Five jack and bore installations of 20” steel gas main through rock.
- 1792 LF HDD installation of 20” steel gas main through rock.
- 1307 LF HDD installation of 20” steel gas main through rock.