Contracted Via: Kiewit

Started: August 2018. 

Completed: April 2019. 

Scope:

  • Drill pad set up, matting, SESC, fencing. 
  • 2,650 LF installation of 34” HDPE via HDD. 
  • Installation of conduit bundle including three each of 8”, 6” and 4” HDPE. 
  • All fusion, debeading, proofing and installation